Resource

Checklist: Local Authority Purchase of Solar Generation Assets

This is a checklist of key issues for any local authorities considering purchasing a solar farm

Checklist

This resource is part of a collection

Print Email Share URL LinkedIn

This is a checklist of key issues for any local authority considering purchasing a solar farm.

This note does not deal with local authorities constructing their own solar farm assets (albeit a number of the same issues would apply). Nor does this note deal with local authority solar PV in a housing setting.

This checklist has been produced by Sharpe Pritchard LLP and is a high-level summary of key issues only. It should not be read as being definitive guidance. Detailed legal advice should be sought before entering into or considering any solar farm purchase and reliance should not be placed on this document in the context of any specific transaction. One thing we want local authorities to take from this note this that local authority purchase of major solar farm assets CAN be done. Not only this but it has been done on a number of occasions already. We have clients that have purchased or developed solar assets both in-house and via a company. We appreciate that developing a major solar project is outside the comfort zone of lots of local authority legal advisers (who are already very busy) as such we are here to help. This checklist provides a high-level summary of some of the key considerations local authority legal advisers might need to consider when considering any purchase of solar farm assets. This list is not definitive but hopefully it provides a good steer as to key issues that may be relevant to any transaction you are contemplating.

Please note this checklist does not cover wider issues such as development of business cases and carbon accounting — which are often material considerations in purchasing any solar farm.

The following phases are considered
image.png

Background to purchase of a solar farm

The following activities occur at each of these phases:

  • Project Development – At this stage a developer will:
    • Pick a site.
    • Tackle land issues (lease vs freehold).
    • Produce the outline design.
    • Seek Planning (this is typically planning consent from the relevant local planning authority under the Town and Country Planning Act regime).
    • Commission surveys including solar feasibility of site (i.e. irradiation).
    • Conduct Environmental Impact Assessments.
    • Obtain a generation licence. This is needed under the Electricity Act 1989 (although there are exemptions for sites with less than 100MW and that does not export more than 50MW). Supply and Distribution licences may also be required (or exemptions therefrom).
  • Contracting – At this stage a developer will put in place key agreements. The key agreements to deliver any solar farm are likely to include the following (note the diagram below assumes a 100% local authority owned structure for simplicity):

image.png

The EPC Agreement is effectively the construction contract to build and install the solar farm (where a local authority is building the assets themselves there may be multiple construction arrangements including an owners engineer to manage outline design). Further equipment agreements may or may not be required in any particular instance.

The O&M Agreement is the contract under which the solar farm will be operated and maintained.

Land agreements will include arrangements for the site on which the solar farm is situated. They may also include rights over land to facilitate access (both for vehicles and any electricity connections).

The Generation Licence is issued by Ofgem. It has standard terms and conditions which are not subject to negotiation. There are certain limited scenarios where the Generation Licence is not required.

Critically a grid connection agreement will be required in most scenarios (only where a project is a pure private wire project will it be the case that a grid connection agreement is not required). Grid connections may allow for import and export. Grid connections can be costly and take a long time to procure. As such grid connections should be implemented as early as possible.

Third Party Power Purchase Agreements will be needed to export the power from the solar assets to a third party. A Power Purchase Agreement is an agreement under which power is sold.

Metering and Asset Management Agreements are typically required in order to ensure the solar assets are operated in accordance with relevant grid rules and requirements.

  • Build – This is the phase in which the solar assets are constructed. This will be undertaken in accordance with the EPC Agreement. Local authorities may require project management services to police the EPC Agreement.
  • Commissioning and Testing – During this phase the works are tested to ensure power output and other deliverables have been achieved. The EPC Agreement should set out detailed completion and commissioning requirements. These should be designed to meet commitments under the PPA as well as requirements of any Grid Connection Agreement and Land Agreements. Performance Guarantees will often be implemented under the EPC Agreement to ensure the contractor is held to required levels of performance.
  • Operations – During this phase the plant will be operated, and power sold under the PPA. The site will be run by the Asset Manager. They will ensure that the solar plant is managed effectively. Where the solar plant also has battery storage then asset management arrangements may be more complex.
  • Decommissioning – At this stage the plant is wound down. It is likely that under planning and Land Agreements that assets will need to be deconstructed the site restored.

Purchase of solar farm assets can happen at a number of times and in a number of ways. Perhaps the safest time to purchase is post Commissioning and Testing. This allows the local authority to ensure that what it is purchasing has been delivered (and cut out construction risk). However it is increasingly common for purchase to occur at the end of the Contracting Phase. Warranties required will vary in each instance.

In terms of the actual sale process this can happen by way of share or asset purchase – although a share purchase of an SPV is most common. Sale processes can be bi-lateral negotiations – i.e. between seller and local authority buyer but are likely to be part of a competitive equity sale process. Under this process, buyers have a limited period to carry out due diligence on work done by the developer up to the end of the contracting stage.

What follows is a checklist of key issues that should be considered for any local authority entering into the purchase of a solar farm. There is a lot of detail behind this, but we hope this list will provide a summary of key issues. Additional issues may (of course) arise on a project-by-project basis.

Checklist area 1 – have development phase basics been undertaken

Unlike other areas and aspects of this Checklist, this Area 1 comprises some of the key initial considerations. Before taking any initial view as to whether a solar farm purchase is viable it is critical to explore at least these initial questions. 

CHECKLIST AREA

CONSIDERED?

Has a suitable width="100%" site been identified?

☐ Yes

☐ No

Have rights for the site been acquired.?

 This should include all land required. Including any land for grid access. Typically the approach may be an option and lease agreement.

☐ Yes

☐ No

Has land due diligence been undertaken?

 This should include usual checks but also a commissioning survey and reports to assess the project’s feasibility.

☐ Yes

☐ No

Has the solar viability of the site been considered?

 For example has a solar resource assessment to assess irradiation levels been done?

☐ Yes

☐ No

Are title reviews of the land available and are any major property red flags identified?

 Eventually a full report should be commissioned on the title or certificate on the title for sites (to establish legal title and assess for whether third party consents or insurance is required).

☐ Yes

☐ No

Environmental Impact Assessments (EIA) – Are they required? Are they undertaken?

☐ Yes

☐ No

Planning application submissions – Have these been made? 

☐ Yes

☐ No

Has planning consent been secured?

 Always check the conditions to any planning consent. Are they appropriate?

☐ Yes

☐ No

Have third party and regulatory consents obtained?

 Third party consents will vary from project to project.

☐ Yes

☐ No

Is a Grid Connection Agreement or Grid Connection Offer in place?

 It is important to look at the exact nature of any Grid Connection Offer or Agreement. This includes timing, cost and constraint risk.

☐ Yes

☐ No

If capital is required for purchase – has an examination been undertaken as to government support schemes and other relevant schemes available?

☐ Yes

☐ No

Have you produced a finance model which reflects provisions made in the key project agreements and which contains assumptions for the cost of financing and revenues.

 It is critical to identify long-term likely revenue streams sufficient to ensure your solar farm can meet its liabilities and likely costs.

☐ Yes

☐ No

Have potential counterparties been identified and are any tendering and negotiation of key project agreements complete?

☐ Yes

☐ No

Checklist area 2 – how are you buying the solar farm

A number of key questions arise as to how the solar farm is to be purchased. This includes local authorities asking all of the following questions:

CHECKLIST AREA

CONSIDERED?

After the purchase, will the local authority be the sole owner of the solar farm?

☐ Yes

☐ No

If the local authority is not to be the sole owner, will ownership be shared with the developer or with a third party? If a third party, will it be another public body?

☐ Yes

☐ No

How will ownership be transferred to the local authority? Will it be a share purchase or an asset purchase?

Typically a share purchase is preferred due to complexity of transferring contracts to a new vehicle however this is not always the case.

☐ Yes

☐ No

Where a share purchase is taking place, has detailed due diligence on the company being acquired been undertaken?

This may include questions in respect of:

  • Existing liabilities.
  • Sufficiency of contracts (including those above).
  • Disclosures regarding any issues or incidents.

☐ Yes

☐ No

Where an asset transfer is taking place, how will assets be transferred and what is the new vehicle in which assets will be held? How will transfer of certain key agreements take place (for example the generation licence)?

☐ Yes

☐ No

Have the procurement implications of an asset or share purchase been contemplated? See further below.

Novation of agreements to local authorities can often count as letting of a new agreement. Similarly a share purchase negotiated with just one developer may raise procurement implications where that developer will be retained in some capacity to continue to provide services. In any event, consideration should be given where bi-lateral negotiations are taking place to make sure the local authority has achieved best value in determining which site to select. 

☐ Yes

☐ No

What corporate vehicle will deliver the solar farm?

Consider the options including a company limited by shares, company limited by guarantee and a limited liability partnership (note there are a number of other options too). Typically such transactions are done by way of a company limited by shares, but LLPs may well present tax and accounting advantages. Notionally the local authority could also hold the assets in house.

☐ Yes

☐ No

How will the local authority fund any purchase price?

Consider cost efficacy and in particular consider:

  • Various public grants.
  • Reserves and PWLB.
  • Bank loans and private finance.
  • Capital from a JV partner.
  • Municipal Bond Agency.
  • Community Bonds.
  • UKIB.

Think about tax and legal powers in conjunction with this.

☐ Yes

☐ No

If working with another local authority to fund the transaction, consider structure options.

Multi-authority roles on projects could entail joint ownership, leasing structures, one authority as offtaker or lender to another. If working together, consider how to bid together and consider:

  • Inter-authority agreements (s.101 LGA 1972)
  • Joint committees (s.102 LGA 1972)
  • Power to make staff available (s.113 LGA 1972)
  • Power to provide goods, services and works to another public body (s.1 Local Authorities (Goods and Services) Act 1970)

☐ Yes

☐ No

At what point in time will you purchase the solar farm? Is it at the end of the Contracting Phase or the end of the Commissioning and Testing Phase? Have you undertaken appropriate due diligence in each case.

This effectively boils down to two options (although variants are possible) for a share purchase transaction as follows:

  • Option 1 – Share Transfer Pre-Construction and Completion: The local authority purchases shares in the SPV that owns the project rights from a developer (i.e. land, planning consent and grid connection offer) at the end of the Project Development/Contracting Phase. They then proceed to construct and operate the solar farm within that SPV.
  • Option 2 – Share Transfer Post-Construction: The local authority purchases the shares in the SPV that owns project rights and constructed and commissioned assets from a developer (i.e. land, planning consent and grid connection offer). They then proceed to operate the solar farm within that SPV.

☐ Yes

☐ No

Checklist area 3 – areas of due diligence/share purchase agreements based on timing of the transaction

Warranties and share purchase arrangements tend to be bespoke when a solar farm project is purchased prior to commissioning and testing. A critical part of review in such a scenario will be ensuring there is a route to put in place all relevant agreements on acceptable width="100%" border=1 terms. What follows are some of the standard concerns where the local authority proposes to purchase the solar farm following testing and commissioning:

CHECKLIST AREA

CONSIDERED?

When does payment occur? Is it all in one lump sum? Typically it may be better to ensure completion has occurred. However in some cases payment in advance can be made subject to appropriate security arrangements.

A particular challenge with entering into a share purchase post-completion can be that developers struggle to raise sufficient finance to build out the project. In this respect, it is not uncommon for developers to seek some payment under an SPA in advance. These funds are used to secure grid connections and undertake other activities (again depending on the advance this can increasingly raise procurement risk – as it can make a share purchase agreement seem more like a works contract). Where any advance payments are made appropriate security would need to be taken (e.g. charges on developer assets). Such securities are not (of themselves) a solution for issues with the project and any advance should be considered in detail.

☐ Yes

☐ No

Does your share purchase arrangement include some or more of the following:

 

Deductions from the purchase price where the plant capacity is lower than expected.

☐ Yes

☐ No

Provision of warranties (including regarding information disclosed).

☐ Yes

☐ No

Provision for certain lease and s.106 payments to be deducted if not discharged.

☐ Yes

☐ No

Provisions about releasing any security from the site.

☐ Yes

☐ No

Provisions about payment flows for payment amounts (i.e. monies to funders first).

☐ Yes

☐ No

Performance warranties.

☐ Yes

☐ No

Limitations on actions of the SPV pre-completion.

☐ Yes

☐ No

Checklist area 4 – procurement issues – in terms of asset ownership MODEL

 All local authorities (and sometimes their wholly owned companies) are subject to the Public Contracts Regulations 2015.

 The Public Contracts Regulations 2015 apply when a contracting authority seeks offers in relation to:

  • A proposed public supply contract.
  • A proposed public works contract.
  • A proposed public services contract.

Under the Public Contracts Regulations 2015, "public contracts" are defined to mean:

"contracts for pecuniary interest concluded in writing between one or more economic operators and one or more contracting authorities and having as their object the execution of works, the supply of products or the provision of services".

 Public contracts must therefore be:

  • in writing; and
  • for pecuniary interest or "consideration".

 Any local authority purchasing a solar farm would need to consider procurement issues whether undertaking a share purchase or an asset purchase.

 Asset purchases are inherently riskier in terms of compliance with the Public Contracts Regulations 2015. This is because when contracts are transferred to any public body this can be construed as a new procurement which may be subject to challenge.

However in respect of a share purchase, when a local authority purchases an SPV from a developer and that SPV is pre-populated with relevant agreements, there are arguments as to whether relevant procurement rules apply.

We set out issues to consider in this regard below:

CHECKLIST AREA

CONSIDERED?

Have you considered the Public Contracts Regulations 2015 in respect of your manner of purchase i.e. asset or share sale? Have you created an audit trail?

☐ Yes

☐ No

If an asset sale, have you conducted an analysis of contracts being transferred for procurement purposes?

☐ Yes

☐ No

If a share purchase, have you considered to what extent the developer has been retained?

If the developer is providing services to the SPV being purchased, consider risk of procurement challenge arising. i.e. can the share purchase be construed as being a services arrangement.

☐ Yes

☐ No

Following purchase, consider the extent to which the solar generator is subject to the Public Contracts Regulations 2015 (for example if it is wholly owned by a public body, it is likely to be caught).

☐ Yes

☐ No

Even if the Public Contracts Regulations 2015 apply in a scenario have you explored the extent to which any exceptions to the obligation to procure might apply?

Have you considered application of thresholds, option to use the negotiated procedure without a prior call for competition, exemptions to the application of the procurement regime (including in respect of regulation 12 of the Public Contracts Regulations 2015)?

☐ Yes

☐ No

Checklist area 5 – revenue agreement

A key part of any purchase of solar assets will be ensuring that the purchasing local authority can make a return on its investment. Local authorities should consider the revenue options for any solar farm they purchase.

Considering the following revenue options may be appropriate:

Form of Agreement

Summary

Notes, Core Risks and Benefits (Summary Only)

Considered Y/N

Private Wire PPA

A direct supply by way of a constructed and purpose-built distribution connection.

 

 

  • This requires a local offtaker with an appropriate demand. Namely, whether this is available depends entirely on geography.
  • A private wire solution would likely involve the offtaker seeking REGO benefits.
  • Reliance on a single large customer(s).
  • Electricity licensing exemptions will likely need to be applied if supply and distribution arises.
  • Avoidance of embedded costs and network charges (however this could change over time if the regulatory regime changes).
  • Back up generation/grid connection could be required due to the intermittent nature of solar generation. This will have a level of capacity charge.
  • The benefit that can be achieved through a private wire approach is largely dependent on the cost of the private wire. If infrastructure is required, this may make the private wire approach uneconomic.
  • Competition laws may require other generators to be permitted to connect.

 

☐ Yes

☐ No

PPA with a Supplier

Enter into a power purchase agreement with a licensed supplier. The supplier pays the generator for its output but will include some allowance for the services it provides.

  • Terms depend on supplier. Most have their own standard form. Price is normally the only material point to move. Though potentially some sharing of residual embedded benefits.
  • This may be temporary as a holding arrangement.
  • Contact with suppliers would need to be made. Can seek different offerings.
  • Premium for longer term arrangement.
  • Pricing and timing of pricing is key. There are a range of options, but typically solar plants receive time of day / seasonal tariffs. There is inherent market risk with this – in particular going forwards – where there is no storage capacity at the plant there is a cannibalisation risk (namely this means that solar plants will all often be generating at similar times and prices will be low). Fixed prices can be possible but come at considerable market chip. SPV will normally take Change in Law risk.

 

 

☐ Yes

☐ No

Sleeved PPA (Assumed to Self but could be to Third Party)

This is where a generator agrees to supply a customer. The agreements are then implemented via a supplier as the party that registers the meters, pays network charges (which it will typically pass through to the counterparties), and a fee for providing the service.

  • Third party supplier needed.
  • Usually long and complex negotiation.
  • Still attract network charges.
  • Greater access to end users or self-supply.
  • Supplier to provide top-up services.
  • Usually reliant on supplier arrangements.
  • Complex interaction with existing wider supply agreements.
  • Sleeving contracts are often extended offtaker agreements, with price negotiations between the generator(s) and end consumer(s) generally creating a fixed price arrangement. Agreements are typically subject to re-negotiation on power price arrangements as well as change in law.
  • A supplier is usually procured to provide top-up and spill arrangements. For their services, a supplier will usually charge a “tolling fee” to cover network charges, imbalance payments, top-up and spill and a service fee.

 

 

☐ Yes

☐ No

Contract for Difference

A CfD results in a payment to the generator if the strike price (a pre-set price reflecting the costs of generating using low-carbon technology) is higher than the reference price (a measure of the average wholesale price of electricity in the GB market). The generator’s income is ‘topped-up’ to the strike price. If the reference price exceeds the strike price, the generator will pay back the difference.

 

  • Guaranteed revenue stream to SPV.
  • Counterparty with LCCC.
  • Protection for Change in Law.
  • Requires an auction round – last solar round was in 2022 and auction rounds are now annual. Solar has secured more than 2.2GW at a price of £45.99/MWh in the latest Contracts for Difference (CfD) auction.
  • Auction must yield an efficient strike price. Auction is competitive. Term is typically 15 years.
  • PPA still required and SPV would have to obtain market price.
  • Subsidy but an accepted one.
  • No hedge for local authority’s own power prices. As such local authority is disadvantaged in periods where market price exceeds Strike Price.

 

☐ Yes

☐ No

Synthetic PPA

A Synthetic PPA is an agreement between a generator and end customer that hedges the wholesale price element of the electricity bill using a contract for difference approach. A PPA will still be required to allocate the generator’s export to a supplier within national settlements.

  • Local authority can obtain Renewable Energy Guarantees of Origin (REGOs) (although this could be done by retirement).
  • Guaranteed revenue stream to SPV.
  • Limited efficacy where local authority wholly own SPV (though cash extraction may still be a benefit in periods of high market price). Greater benefit where SPV is not wholly owned.
  • Local authority can extract upside in the event of high market price. Local authority is exposed on low market price.
  • Both parties still require PPAs – these must identify wholesale price.
  • Enhanced procurement risk (though arguably a financial instrument). Enhanced subsidy risk although this can be mitigated. Critical to set Strike Price at a defensible level.

 

☐ Yes

☐ No

Traded Asset with route to market agreements (RTMA)

Mixed and optimised trading. This can take place via several routes to market – including the capacity market, balancing mechanism, power exchanges, dynamic response and other ancillary service. This is typically done via an aggregator.

  • Higher risk.
  • Shifting market – i.e. changes to ancillary services.
  • Back up of revenue stack.
  • Solar can bid in capacity market.
  • May be more efficient alongside battery storage.
  • Local authority to procure an aggregator – typically done on a tolling or profit share basis.
  •  

☐ Yes

☐ No

 Local authorities should also consider the procurement issues arising under the Public Contracts Regulations 2015 from selecting any one or more of these options. For example, if a local authority were to elect to sell power from its solar farm to itself it would need to consider whether the purchase of this power was subject to procurement rules. Procurement issues are also likely to arise in any sleeving arrangement.

Checklist area 6 – other agreements

We do not set out the details of every single agreement in this checklist and the requirements for such agreements. However we set out below the list of core contractual agreements (in addition to the Revenue Agreements (above)) that any solar farm project would likely require as a minimum. We have summarised what each of these agreements do above.

Local authorities should consider whether any solar farm they are to purchase has (or will have) the following or equivalents (and if not, they should consider why this is the case):

CHECKLIST AREA

CONSIDERED?

Land Agreements for the Main Site – This may include

Register to access the full article

Designed to aid Local Authorities in developing robust, evidence-based plans to enable Net Zero.

Register now

Already have an account? Login

Free UK Local Authority access

Register now
  • Guest preview of selected publicly available resources
  • Full library of 1,000+ articles
  • CPD accredited e-learning courses
  • Case studies
  • Discussion forum

Net Zero Go is managed by Energy Systems Catapult, funded & backed by Department for Energy Security & Net Zero, and co-created with Net Zero Hubs, local authorities, and industry experts. Our team is here to help increase the capacity, capability & collaboration of UK local authorities delivering local Net Zero energy projects, and amplify the reach of the work by others in the space by referencing them.

Net Zero Go is a registered trademark of Energy Systems Catapult

Funded by

Managed by

In partnership with

© Energy Systems Catapult 2025